Maintenance process .

Update:Mar 14,2022
Summary:1、 Preparations before maintenance: 1. Prepare the first draft of the maintenance plan one and a half months before the maintenance, and specify the ......
1、 Preparations before maintenance:
1. Prepare the first draft of the maintenance plan one and a half months before the maintenance, and specify the maintenance plan before the maintenance
Work objectives; Person in charge: leader in charge of branch plant and security department
1.1 one and a half months before the maintenance, carry out detailed spot inspection on the equipment in the area and make relevant records
Recording; Responsible person: relevant technicians of branch factory and security department
1.2 collect the problems existing in the current equipment from each team and deal with them in time during operation
If it cannot be handled, the monitoring scheme shall be made and incorporated into the maintenance plan;
Person in charge: leader of branch plant and security department
1.3 carry out regular inspection of relevant equipment and declaration and procurement of medium and long-term spare parts;
Person in charge: leader in charge of branch plant and security department
2. One month before the overhaul, the production quality department shall take the lead to review the overhaul plan and compare it with the "five
Carry out unified dispatching and deployment for the "implementation" work, with the participation of relevant technical personnel of all departments;
Responsible person: production quality department
2.1 in principle, maintenance items that can be handled at ordinary times are not included in the maintenance plan, and
The equipment affecting the shutdown of the main engine that cannot be inspected at ordinary times must be included in the maintenance plan